Hertsmere plans to use a government extension and send its Local Plan to inspectors by 31 March 2027. Its new timetable puts adoption in October 2028.
Hertsmere Borough Council plans to take three extra months to send its new Local Plan to the government. The submission deadline would move from 31 December 2026 to 31 March 2027. A revised timetable puts adoption of the plan in October 2028.
Cabinet will decide on Wednesday 25 November. The papers are in the Cabinet agenda for that meeting.
The change does not alter the deadline for comments. The current consultation on the plan still closes at 11.59pm on Thursday 19 November, tomorrow night.
Why the deadline is moving
The Housing Minister, Matthew Pennycook, wrote to every council leader on 23 October. Plans still being prepared under the old rules had to be submitted by 31 December 2026. He has now given a three-month extension to councils whose final consultation ends by that date.
In his letter he said 56 plans had reached that pre-submission stage this year. “There should be no expectation of further extensions beyond the end of March,” he wrote. “This is the last opportunity for areas seeking to progress plans to submission in the legacy system.”
Hertsmere qualifies because its consultation ends on 19 November. Councils taking the extension must send an updated timetable to the government by the end of November.
The council’s report says sticking to December would put the plan “at significant risk”, because there would be little time to prepare the submission. It adds that the council had worked to the original deadline “because it had no other option (until now)”.
The item is being treated as urgent, so it cannot be called in. The government asked for a response within days, and the next Cabinet is not until December.
The new timetable
The revised Local Development Scheme sets out the programme. Reading from its chart:
- December 2026 to February 2027: the council considers the comments made in the current consultation. The plan goes back to Cabinet and Full Council before it is submitted.
- By 31 March 2027: submission to the government, starting the examination.
- September and October 2027: the inspectors set out their matters, issues and questions.
- November 2027 to January 2028: public hearing sessions.
- June and July 2028: the inspectors’ main modifications.
- October 2028: adoption.
The council says this is an “aspirational” programme. Once the plan is submitted, the inspectors run the timetable. The report expects the schedule may need revising again during the examination, partly because so many councils are submitting at the same time.
Until a new plan is adopted, the borough’s current plan stays in force. That is the Core Strategy of 2013, the Elstree Way Corridor Area Action Plan of 2015 and the site allocations and policies document of 2016.
What it means for you
- Comment by tomorrow night if you want the inspectors to see your view. The deadline is 11.59pm on Thursday 19 November. Our guide to commenting on the Hertsmere Local Plan sets out the three ways to respond.
- Planning decisions carry on under the current plan. Applications are still decided against the 2013 to 2016 documents, with the draft plan given limited weight for now.
- There will be a chance to take part again. Public hearings are pencilled in for November 2027 to January 2028.
Have your say